Fire Substation Building Committee approves change order, contractor payment.
Fire Substation Building Committee unanimously approves change order and contractor payment as construction progresses. The committee voted to accept Change Order Number 11 totaling $4,049.97, which includes a $4,057.93 countertop addition to the non-ADA toilet room and a $7.96 credit for flooring
Fire Substation Committee · Meeting of March 11, 2026
CHARLTON — Fire Substation Building Committee unanimously approves change order and contractor payment as construction progresses. The committee voted to accept Change Order Number 11 totaling $4,049.97, which includes a $4,057.93 countertop addition to the non-ADA toilet room and a $7.96 credit for flooring adjustments in the training and meeting room. Pay Requisition 11 for $320,460.09 was also unanimously approved pending final review by CHA and Context.
Project expenditures now total $7,055,400 of a roughly $18.5 million scope, with construction at approximately 38 percent completion; the project team is investigating potential schedule impacts recently received.
In the full story:
- The complete report — 272 words
Source: the Fire Substation Committee meeting of March 11, 2026, compiled from the official minutes.
Members read the rest of this story and every Charlton meeting we cover, in full.
Become a memberAlready a member? Sign inA 30-day free trial needs a payment method. After it, your membership renews at the price shown at checkout until you cancel, which you can do anytime from your account. Subscription terms
Share this brief
Know someone in Charlton who follows town government? Share Townbrief Charlton: they can sign up free.