Fire Substation Building Committee approves $67,935 in change orders.

Fire Substation Building Committee approves $67,935 in change orders and transfers contingency funds. The committee unanimously approved Change Order Number 9, comprising three separate proposals for interior finishes, porch construction, and sprinkler modifications at a combined cost of

Fire Substation Committee · Meeting of January 14, 2026

CHARLTON — Fire Substation Building Committee approves $67,935 in change orders and transfers contingency funds. The committee unanimously approved Change Order Number 9, comprising three separate proposals for interior finishes, porch construction, and sprinkler modifications at a combined cost of $67,935.97. Andrew Golas reported that reconciliation of expenses between the Town and CHA revealed unanticipated borrowing costs, prompting a unanimous vote to transfer $43,612 from contingency to administration.

The project stands at approximately 38 percent complete with $4,965,311 expended to date and $8,081,946 remaining; contingency balance stands at $2,367,350.

In the full story:

  • The complete report — 328 words

Source: the Fire Substation Committee meeting of January 14, 2026, compiled from the official minutes.

Members read the rest of this story and every Charlton meeting we cover, in full.

Become a member

A 30-day free trial needs a payment method. After it, your membership renews at the price shown at checkout until you cancel, which you can do anytime from your account. Subscription terms

Share this brief

Email Text Facebook X

Know someone in Charlton who follows town government? Share Townbrief Charlton: they can sign up free.

Get Charlton's town government news by email, free. One briefing each morning.

Share this story

Email Text Facebook X

Anyone can open a shared story. Members' stories show the free part and a sign-up line to people who are not members.